Work Session Progress
As of August 31
- All sections have the track for the main line loops.
- All sections have the base wiring to power the layout
- All wiring has been checked for continuity and correct plug alignment
If we had to set up the layout right now we could put it together and operate a DC train on each track.
Work has started on a scenery base
Work has started on the automated trolley track.
We are scheduled to move in to the new building September 25.
The formal building opening will be in the first week of November